The withdrawn opinion was titled "Tribal Treaty and Environmental Statutory Implications of the Dakota Access Pipeline." Although it helped the tribes in their lawsuit, it was not the basis for a federal judge's decision to order the Army Corps to undertake a more thorough review of the final portion. Instead, Judge James Boasberg said the agency failed to take a "hard look" at issues raised by the tribes, including treaty rights, oil spills and environmental justice. Despite the ruling, the Army Corps has yet to heed the judge's directive. As of Tuesday morning, more than a month after the decision, the agency has not provided notice of its intent to prepare an environmental impact statement for the final portion of the pipeline. In a new court filing, the Trump administration indicated that the review is still on the table. But it looks like a revised analysis is far off, according to the Department of Justice. "The Corps is actively evaluating the issues remanded to it by the court and expects to complete its review of those issues by late December 2017," government attorneys wrote on Monday. Oil started flowing through the pipeline on June 1, thanks to the Trump administration's approval of the final portion. The wealthy backers of the project say oil should continue flowing while the Army Corps conducts its review. "A shutdown while the Corps provides additional explanation for its determinations, under a statute that calls only for a process and not a particular substantive outcome, would add insult to injury," attorneys for Dakota Access wrote on Monday. The Standing Rock Sioux Tribe and the Cheyenne River Sioux Tribe have until August 7 to respond to the new filings, according to a schedule adopted by the judge last month. Both tribes want oil to stop flowing until the Army Corps addresses their concerns. "Never before have so many tribes stood together in the spirit of peaceful but insistent residence," Standing Rock Chairman Dave Archambault II wrote in a letter to supporters last week. "Never before have so many non-Native allies from around the world come to stand with us and acknowledge that the unfair mistreatment is beyond tolerable and must not continue." Additional briefing will conclude on August 28 so a decision on the status of the pipeline is also far off. Office of the Solicitor Documents:
M-37038 - Tribal Treaty and Environmental Statutory Implications of the Dakota Access Pipeline (December 4, 2016)
Temporary Suspension of M-37038 (February 6, 2017)
Withdrawal of M-37038 (July 7, 2017) Federal Register Notices:
Notice of Termination of the Intent To Prepare an Environmental Impact Statement in Connection With Dakota Access, LLC's Request for an Easement To Cross Lake Oahe, North Dakota (February 17, 2017)
Notice of Intent To Prepare an Environmental Impact Statement in Connection With Dakota Access, LLC's Request for an Easement To Cross Lake Oahe, North Dakota (January 18, 2017) Dakota Access Pipeline Approval Documents:
Department of Justice Notice | Department of the Army Approval Memorandum | Notice of Termination of EIS for Dakota Access Pipeline | Easement Letter to Congressional Leadership White House Documents:
Presidential Memorandum Regarding Construction of the Dakota Access Pipeline (January 24, 2017)
Presidential Memorandum Regarding Construction of the Keystone XL Pipeline (January 24, 2017)
Executive Order Expediting Environmental Reviews and Approvals For High Priority Infrastructure Projects (January 24, 2017)
Presidential Memorandum Regarding Construction of American Pipelines (January 24, 2017)
Presidential Memorandum Streamlining Permitting and Reducing Regulatory Burdens for Domestic Manufacturing (January 24, 2017)
Press Release: President Trump Takes Action to Expedite Priority Energy and Infrastructure Projects (January 24, 2017)
Join the Conversation
Related Stories
President
Trump doesn't seem to know where Dakota Access Pipeline goes (July 14, 2017)North Dakota still hoping to secure taxpayer funds for #NoDAPL response (July 14, 2017)
YES! Magazine: Native activists continue to pressure banks on pipelines (July 10, 2017)
Albert Bender: Judge waited for oil to flow through Dakota Access Pipeline (July 6, 2017)
Dakota Access still fighting small fine for disturbance of tribal artifacts (July 5, 2017)
Officials in North Dakota claim ignorance on Dakota Access security firm (June 29, 2017)
Dakota Access security firm was denied license but kept working anyway (June 28, 2017)
Tribes in for long haul as oil continues to flow through Dakota Access Pipeline (June 23, 2017)
Cheyenne River Sioux Tribe welcomes 'victory' in Dakota Access Pipeline case (June 16, 2017)
Mark Trahant: Dakota Access decision offers a chance to return to respect (June 16, 2017)
Jacqueline Keeler: Connecting the Dakota Access Pipeline to history (June 15, 2017)
Indian Country celebrates as judge orders environmental review of Dakota Access Pipeline (June 15, 2017)
Albert Bender: Judge drags his feet in Dakota Access Pipeline case (June 12, 2017)
Dakota Access faces fines for disturbing artifacts in North Dakota (June 8, 2017)
President Trump put wealthy firm first in approving Dakota Access Pipeline (June 7, 2017)